Explosion risk assessment (R4227-1 et seq. of the code)
work) and drafting of the document relating to protection against
explosions (DRPCE) according to the CNPP EVAREX method (directive 1999/92/EC)
The DRPCE must report on all actions taken
implemented on site to protect the worker against the risk
explosion. As such, it constitutes an annex to the DUERP (Single Document for Risk Assessment).
Implementing decree no. 2002-1553 of December 24, 2002
specifies its content. It must include, among other things:
- The classification of hazardous areas.
- The determination and assessment of explosion risks.
- The nature of the measures taken to achieve the objectives of the directive and to ensure that the use of work equipment is safe.
- the terms and rules according to which the places and the
Work equipment, including alarm devices, is designed, used and maintained to ensure safety.
Prerequisites
Any business using combustible dust, flammable chemicals or processes that could lead to a risk of explosion.